Shell Only Package
Is our shell only package right for you?
Our shell only package is perfect for individuals with a trade background or anyone looking to cut costs on their final product. Our specialised package has been crafted with careful consideration to benefit those in these specific situations. With our package, you can streamline your process and maximise your savings without sacrificing quality. Learn more about how our package works by reading the information below.
Step 1
Site Mark out and Excavation
This involves the positioning and setting out of the pool. Our experienced excavator operators then complete the excavation.Step 2
Formwork and Steel Fixing
The shell of the pool is formed via the formwork and steelwork. The pool will slowly start to take shape in readiness for the next stage.Step 3
Pre-Plumb
Plumbing and pipework takes place, pipework is placed in strategic places to ensure successful operation of the pool once complete. Earthing of the reo bars is done at this stage also.Step 4
Shot Crete and Handover
With the steel and shell now laid out, the concrete pour and spray is done. At this stage you will visually start to see the pool taking shape. After this stage is complete, we recommend a minimum 4 week “curing period” to allow the concrete to achieve its ultimate strength.